Drake Field Artificial Turf Project Delayed, As Turf Supply Shortage Hits Contractor

Parks and Recreation Director Nathan Powell stated the corporate that was chosen to install the synthetic turf (Learn More Here) at Drake Field, Mid-American Sports Construction, couldn’t get synthetic turf this year as initially expected. Despite the uncertainty of when the contractor will get the turf to install, Powell anticipates it’s going to arrive for crews to complete the roughly $410,000 undertaking by the spring.

“They can’t get synthetic turf this year as they expected. They could be capable to get it by December. Nobody believes that it’s going to take till June to get it executed, and so they assume they are going to get the turf earlier than December,” Powell stated during the Aug. 12 Parks and Recreation Board assembly. “They may even get it performed this yr, however they can be on it as soon as they have the precise temperature within the spring.”

Sports Complex Supervisor Jeremy Nielsen stated Mitchell’s Drake Field is certainly one of 12 that the Missouri-primarily based sports activities field building company can’t get installed by the fall.

Although the turf has yet to arrive, crews will begin the dirt work that needs to be completed for the turf to be put in within every week. Nielsen mentioned the dirt work that crews are set to begin Monday will permit the turf to be put in within two weeks when it does arrive. However, he famous that it can even hinge on weather situations.

“They say forty degrees is the ideal temperature to install, and it’ll take about two weeks to place the turf in. It doesn’t must be forty degrees for 2 weeks straight, it may well have some fluctuating temperatures in that timeframe,” Nielsen said. “The turf company is saying they are a hundred and twenty days out to get the turf, which might put it round December.”

The venture entails installing artificial turf in the infield and round backstop space and bullpens. The outfield will have roughly 6-feet of turf, while the remaining will remain grass. In addition, the backstop and a few fencing across the diamond will be replaced as a part of the overall mission.

“The color of the turf will go from brown to green for a 6-foot arch strip that may go into the outfield,” Nielsen said.

Bringing synthetic turf to Drake Field, which sits next to Cadwell Park, has been a shared objective among native baseball leaders and teams that utilize the baseball diamond. Mitchell Post 18 head coach Luke Norden stated the turf infield will give Drake Field the flexibility to handle video games and practices nearly immediately after a rain event, which is a challenge both Mitchell’s baseball teams have come up in opposition to with the prevailing grass infield.

Dakota Wesleyan University and Mitchell Baseball Association each pledged $65,000 donations for the turf project, whereas the Drake family, who the sphere is named after, pledged $30,000. The Exchange Club also pitched in with a pledge of $15,000. Once the challenge is full, DWU and Mitchell Baseball Association could have their crew logos positioned on the infield. The Drake household will also have a logo applied to the infield.

Through the Aug. 12 Parks and artificial lawn Recreation Board meeting, Board President Chris Retterath addressed his concern of where Dakota Wesleyan University and Mitchell Baseball groups would play in 2022 if Drake Field is under development till June 1, 2022 or past that time frame. Nielsen stated Cadwell Park would function the alternative option for DWU baseball, if the turf challenge isn’t completed until June 2022.

Powell advised establishing a hard deadline for the project’s completion date to June 1, 2022. If the contractors aren’t ready to install the turf by the June 1, 2022 deadline, Powell mentioned a $one hundred to $150 payment would be tacked on for synthetic turf each day the mission completion date stretches past the deadline.